Water Main Replacement, Clifton and Passaic: Paulison Ave (Highland Ave to Lincoln St) Phase 1

Project Overview

Project Number: 25-B-10

Estimated Budget: $4 million

Anticipated Start: July 2026

Anticipated Completion: September 2026

Contractor: PACT One


Project Description:

We’re replacing an existing water main located on Paulison Avenue between Highland Avenue and Lincoln Street upgrading the water system in Clifton and Passaic to make it stronger, safer, and ready for the future.

This project includes the replacement of 4,800 LF of an existing critical 16-inch water main installed in the mid 1920’s with a new 12-inch ductile iron water main, and new valves, hydrants and service connections. The anticipated construction costs are estimated to be around $4 million.

Replacing this critical section of pipeline will help minimize service disruptions caused by aging infrastructure and improve the utility’s ability to operate and maintain the system. These upgrades will also strengthen fire protection capabilities and support continued investment in dependable water service for the surrounding communities.


Project Overview

Project Number: 25-B-10

Estimated Budget: $4 million

Anticipated Start: July 2026

Anticipated Completion: September 2026

Contractor: PACT One


Project Description:

We’re replacing an existing water main located on Paulison Avenue between Highland Avenue and Lincoln Street upgrading the water system in Clifton and Passaic to make it stronger, safer, and ready for the future.

This project includes the replacement of 4,800 LF of an existing critical 16-inch water main installed in the mid 1920’s with a new 12-inch ductile iron water main, and new valves, hydrants and service connections. The anticipated construction costs are estimated to be around $4 million.

Replacing this critical section of pipeline will help minimize service disruptions caused by aging infrastructure and improve the utility’s ability to operate and maintain the system. These upgrades will also strengthen fire protection capabilities and support continued investment in dependable water service for the surrounding communities.


Questions About the Project

Have questions about the Water Main Replacement, Clifton and Passaic: Paulison Ave (Highland Ave to Lincoln St) Phase 1 project?

We're here to help and will respond with the most up-to-date information as soon as we can.



You need to be signed in to add your question.