Water Main Replacement, Mountainview Dr, Clifton

Project Overview

Project Number: 25-B-02

Estimated Budget: $2.4M

Anticipated Start Date: September 2026

Anticipated Completion: Q1 2027

Contractor: J Fletcher Creamer & Son


Project Description:

We’re replacing approximately 4,500 linear feet of existing 6-inch cast iron pipe on Mountainview Drive area in Clifton.

This project includes the replacement of 4,500 LF of existing 6-inch water main installed in 1951 with a new 8-inch ductile iron water mains, new valves, hydrants, and a new 1-inch service connections. The anticipated construction costs are estimated to be around $2.4 million.


Project Overview

Project Number: 25-B-02

Estimated Budget: $2.4M

Anticipated Start Date: September 2026

Anticipated Completion: Q1 2027

Contractor: J Fletcher Creamer & Son


Project Description:

We’re replacing approximately 4,500 linear feet of existing 6-inch cast iron pipe on Mountainview Drive area in Clifton.

This project includes the replacement of 4,500 LF of existing 6-inch water main installed in 1951 with a new 8-inch ductile iron water mains, new valves, hydrants, and a new 1-inch service connections. The anticipated construction costs are estimated to be around $2.4 million.


Questions About the Project

Have questions about the Water Main Replacement, Mountainview Drive, Clifton project?

We're here to help and will respond with the most up-to-date information as soon as we can.



You need to be signed in to add your question.