Water Main Replacement, Fordham Road, Clifton
Project Overview
Project Number: 25-B-02
Estimated Budget: $800,000
Anticipated Start: Q2 2026
Anticipated Completion: Q3 2026
Project Description:
We’re replacing approximately 1,650 linear feet of existing 6-inch on Fordham Road from Valley Road to Ploch Road.
This project includes the replacement of 1,650 LF of existing unlined cast iron 6-inch water installed in 1951 with a new 8-inch ductile iron water main, new valves, hydrants and new service connections. The anticipated construction costs are estimated to be around $800,000.00.