Project Number: 25-B-02

Estimated Budget: $2.1 million

Anticipated Start: Q2 2026

Anticipated Completion: Q3 2026


Project Description:

We’re replacing approximately 3,100 linear feet of existing 6-inch cast iron from Paulison Avenue to 3rd Street and on Madison Avenue from Hawthorne Avenue to Jewett Ave with a new 12-inch ductile iron main.


This project includes the replacement of 3,100 LF of existing 6-inch water main installed between 1906-1911 with a new 12-inch ductile iron water mains, new valves, hydrants, and a new 1-inch service connections. The anticipated construction costs are estimated to be around $2.1 million.



Project Overview

Project Number: 25-B-02

Estimated Budget: $2.1 million

Anticipated Start: Q2 2026

Anticipated Completion: Q3 2026


Project Description:

We’re replacing approximately 3,100 linear feet of existing 6-inch cast iron from Paulison Avenue to 3rd Street and on Madison Avenue from Hawthorne Avenue to Jewett Ave with a new 12-inch ductile iron main.


This project includes the replacement of 3,100 LF of existing 6-inch water main installed between 1906-1911 with a new 12-inch ductile iron water mains, new valves, hydrants, and a new 1-inch service connections. The anticipated construction costs are estimated to be around $2.1 million.



Questions About the Project

Have questions about the Water Main Replacement, DeMott Street, Clifton project?

We're here to help and will respond with the most up-to-date information as soon as we can.



You need to be signed in to add your question.