Water Main Replacement, DeMott Street, Clifton
Project Overview
Project Number: 25-B-02
Estimated Budget: $2.1 million
Anticipated Start: Q2 2026
Anticipated Completion: Q3 2026
Project Description:
We’re replacing approximately 3,100 linear feet of existing 6-inch cast iron from Paulison Avenue to 3rd Street and on Madison Avenue from Hawthorne Avenue to Jewett Ave with a new 12-inch ductile iron main.
This project includes the replacement of 3,100 LF of existing 6-inch water main installed between 1906-1911 with a new 12-inch ductile iron water mains, new valves, hydrants, and a new 1-inch service connections. The anticipated construction costs are estimated to be around $2.1 million.